HS2 viaduct installed over open motorway in claimed UK first

Sarah Mason 17th Dec, 2025   0

ENGINEERS working for the HS2 project claimed a UK-first when they slid an enormous 4,600-tonne viaduct across the M6 without closing the motorway.

The 17 hour-long operation was the culmination of an epic three-stage process to assemble and install the 315-metre East deck of the M6 South viaduct, which will carry high-speed trains heading to Birmingham.

While the previous slide had required a weekend closure of the main carriageway, the team – led by HS2’s main work contractor Balfour Beatty VINCI (BBV) – worked closely with National Highways to develop the ‘fully restrained’ process which allowed them to safely slide the final section above the moving traffic.

It is thought to be the first time this technique has been used on a UK motorway.

To deliver this, they initially closed the M6 overnight between Junctions 4 for Coleshill and 5 for Castle Bromwich on December 11 to shift the viaduct slightly forward by twelve metres.

This was to ensure that both ends of the enormous beam were fully supported on concrete piers during this weekend’s slide.




The viaduct was then pushed the rest of the way across the busy motorway on Saturday at a speed of 13 metres per hour, with only the M42 slip closed during the weekend.

The successful operation means the project to construct the M6 South viaduct has reached the halfway point. Over the next year, the same process will be repeated, with a parallel West deck slid into position alongside the first one to carry trains heading south.


Russell Luckhurst, the BBV engineer leading the delivery of the works, said: “We’re all feeling a huge sense of pride after sliding a 4,600-tonne viaduct into its final position this weekend. The third and final slide of the East deck viaduct was delivered over a live motorway for the first time in the UK, making this achievement even more special.

“Using this ‘fully restrained’ technique meant we were able to keep disruption to an absolute minimum. Our focus will now turn towards the neighbouring West deck viaduct, which will be launched in multiple phases throughout 2026, as well as the East deck finishing works.”

Mark Wild, HS2 Ltd’s chief executive, is currently leading a comprehensive reset of the programme – making sure the new railway is built as efficiently as possible and for the lowest reasonable cost. Over the last year, HS2 has focused on safely boosting levels of productivity across the construction programme.

The M6 South viaduct has been designed in stages to increase efficiency and reduce disruption for motorists. Each section is assembled to one side before being pushed out over the motorway, with the next section added behind it.

In the latest phase, the team moved the viaduct using a series of winches, known as strand jacks. To reduce friction, the structure was slid across non-stick pads, using a material usually found on the surface of a household frying pan.